(Information through Nov. 30, 2019)
Date authorized: July 26, 2018
Project Authorization: $ 1,960,000 (includes property acquisition, back taxes, equipment, and capital improvements.)
Delivery Method: Design/Bid/Build
Design Firm: The Clark Enersen Partners
Contractor: Crossland Construction Company
Completion Date: Q1 2020 (substantial completion)
Future Pending Action(s):
Update: Construction is underway. New exterior metal panels, fencing and paving improvements are complete. Work continues on the interior of the building and the site. The facility is anticipated to be open for business in Q1 2020.