Date Authorized: Project approved through Capital Improvement Plan
Project Authorization: $1,260,780
Delivery Method: Design, Bid, Build
Design Firm: The Clark Enersen Partners
Contractor: TBD
Completion Date: Substantial Completion anticipated May, 2021
Future Pending Action(s): No action required from BOCC
Update: The scope of the project includes replacement of three picnic shelters along the north shore of Shawnee Mission Lake, accessibility and parking improvements. The start of construction is anticipated for September 2020.