(Information through Nov. 30, 2019)
Date authorized: July 6, 2017
Project Authorization: $4,300,000 (includes property acquisitions, demolition, and parking lot
construction)
Delivery Method: Design/Bid/Build
Design Firm: Treanor HL
Contractor: TBD
Completion Date: Q3 2020 (substantial completion)
Future Pending Action(s): Construction contract
Update: JE Dunn is currently using the area north of the New Courthouse as a staging area for the New Courthouse site. The budget for the remaining parking lot construction is approximately $1,200,000. In order to meet the Courthouse schedule and the needed sequencing of work, JE Dunn is able to incorporate this parking lot construction within the existing GMP for the Courthouse.