(Updated July 31, 2020)
Date authorized: 11/15/2017 (approved $1,000,000 from JCPRD’s capital improvement fund and $1,051,627 from The Parks and Recreation Foundation of Johnson County)
Project Authorization: $2,051,627
Delivery Method: Design, Bid, Build
Design Firm: SFS
Contractor: Loyd Buildings, Inc.
Completion Date: Substantial Completion May 21, 2020
Future Pending Action(s): No action required from BOCC
Update: Construction of the tower is complete. A Certificate of Occuancy was issued by Johnson County Codes on June, 18, 2020. The observation tower was opened for public use on Friday July 17.