Engineering Public Projects: Lone Elm and 180th

Little Bull Creek #1 - Lateral Sewer District #2

Current Project Status

-A Public Hearing regarding a Special Assessment for Lateral Sewer District No. 2 of Little Bull Creek No. 1 was held July 23.

The method of assessment for this district is the Per Homesite Method. This method recognizes the equal benefit to each homesite and apportions costs equally. All 65 homesites within Lateral Serwer District No. 2 of Little Bull Creek No. 1 will pay an equal share of the pressure main costs and the 56 homes that had pumps installed by this project will in addition pay equally for the pump system costs.

Any questions about this project should be directed to Johnson County Wastewater's Senior Engineering Technician at 913-715-8556.

Background and Objectives

Following several requests for information meetings by area residents, Johnson County Wastewater staff studied how this area might be best served by sanitary sewers, planned proposed sewers and developed cost estimates. The project will serve approximately 38 acres and 63 properties with low pressure sewers, including all existing homes and any vacant lot that could be developed in the sewer district.

The Kansas Department of Health and Environment (KDHE) administers a State Revolving Fund Loan Program (SRF) and has approved financing for this project. The program allows for a low interest loan from the state for a 20 year period to residents in the proposed district. It also calls for a 40 percent principal forgiveness (essentially, a grant) on the project. This program also offers financing for the installation of the grinder pump unit and connection fees for each home. Project cost sheet 

A petition bearing signatures of owners of 57.9 percent (51 percent is the minimum required) of the land area in the proposed district requesting the installation of low pressure sewers was submitted to the County. A Public Hearing was held on Aug. 25, 2011. On Sept. 22, 2011, the Johnson County Board of Commissioners voted to approve the Lone Elm Pressure Sewer project. On March 8, 2011, the Board approved the KDHE SRF Loan Agreement for the project.